Quality Gates
A quality gate is a set of conditions on measured values, such as "Critical issues equal to 0". After an assessment, IZ Suite compares the application's measured values with the gate for its technology and records a pass or a failure. Use this tab to see which applications each gate judged, investigate failures and adapt the conditions for each technology.
Open it from Operations → Quality Control → Quality gates in the sidebar.

Summary Tiles
Click a tile to filter the gate library.
Available gates
All gates that match the current search and technology.
Supplied standards
Built-in gates supplied with IZ Suite, one default per technology.
Your standards
Custom gates your team maintains.
Gate Library
Status
All gates, Custom, Supplied or Needs definition (gates without conditions).
Technology
The technology the gate measures, for example Apex, Mule or CloudFormation.
Search quality gates
Finds gates by name.
Saved filters and Save filters keep a combination of filters for later. Refresh reloads the list, Columns chooses the visible columns and Export downloads the list.
Quality gate
The gate name and a Supplied or Custom tag. Click the name to open the gate's details.
Technology
The technology the gate applies to.
Conditions
The number of conditions, or Needs definition when there are none.
Last updated
When the gate last changed. The list shows the most recently changed gates first; click Last updated or Quality gate to sort by it.
Latest assessment use
How many applications were assessed with the gate in their latest assessment, how many passed and failed, and in how many organizations it is the default. Click it to review usage.
Actions
Edit gate (View gate when you can only view) and Assign to organizations.
Gate Details
Click a gate's name, condition count or usage to open its details. The drawer shows the technology, whether the gate is supplied or custom, when it was last updated and its conditions. Application usage & defaults shows:
Applications assessed, Passed this gate and Failed this gate for the latest recorded assessments.
Applications using this standard: each application or version whose latest assessment used this gate, filtered by All, Passed, Failed or Not evaluated.
Organization defaults: the organizations that use this gate by default.
Edit / inspect definition opens the gate editor. Assign to organizations opens the assignment described below.
Create a Quality Gate
Click Create quality gate.
Enter the Gate name. Required.
Choose the Technology. Required. Conditions measure this technology's metrics, so choose it first.
Under Overall code, click Add condition and fill in the condition (see Condition Fields below). Repeat for each condition.
Optionally, under New code, add the conditions that judge pull requests.
Click Create quality gate. The gate and its conditions are saved together and the gate opens in the editor.

Condition Scopes
Overall code
Branches and versions are judged on these conditions: every measured value must satisfy its condition. Findings under an approved, unexpired exception do not count.
New code
Pull requests are judged on these conditions alone: issue counts for the findings that are not open on the target branch, and the vulnerable dependencies or deprecated assets the target branch does not have. Without new-code conditions, or when the target branch has not been scanned, a pull request is judged on the overall conditions, using all of its findings.
Condition Fields
Measured value
The metric to check, shown with its output type. Required. Boolean metrics cannot be chosen. New-code conditions use issue counts per severity, Vulnerable Dependencies or Deprecated Assets.
Required comparison
Is Greater Than, Is Greater Than Equal To, Is Less Than, Is Less Than Equal To or Is Equal To. Required. Text metrics allow Is Equal To only.
Required value
The value to compare with. Required. A numeric metric needs a valid number.
The dialog shows the resulting requirement in words, for example "Require Critical Issues to be equal to 0".
Vulnerable Dependencies and Deprecated Assets
Two measured values let a gate fail on the risks shown on an application's Risk & lifecycle panel:
Vulnerable Dependencies
The application's own components that match a vulnerability advisory.
Deprecated Assets
The deprecation and lifecycle rules that apply to the application: deprecated components it uses, and the application itself when a rule deprecates it.
They are counted only for a technology whose gate has one of these conditions; other gates are not affected.
IZ Suite counts them when it judges the gate, from the components the assessment collected, and records the counts with the assessment. A later advisory or rule changes the next assessment, not a recorded result.
Only the application's own risk counts, not the risk of the applications it connects to. Matches reviewed as Fixed, Won't fix or Exception, and rules not yet in effect, do not count.
As New code conditions, they count only what a pull request adds: the vulnerable dependencies and deprecated assets its target branch does not have.
A failed condition names what was found, for example "1 - Vulnerable Dependencies (log4j-core 2.14.1: CVE-2021-44228), which is greater than configured value of 0". See Risk & Lifecycle for the advisories and rules behind them.
Edit a Quality Gate
Click Edit gate on the gate's row.
Change the Gate name and click Save gate details.
On Required conditions, use Add condition, Edit condition or Remove condition in each scope. Each change is saved when you confirm it.
The Technology cannot be changed while the gate has conditions; remove them first. The Application usage & defaults tab shows the same usage as the details drawer and Assign organization defaults.
Assign a Gate to Organizations
Click Assign to organizations on the gate's row. The Activate Profile In Org dialog lists the organizations that already use the gate under Profile active in Organizations.
Choose one or more organizations in the Add organization to profile field.
Click Add Organizations.
Assignment controls which organizations use the gate for future assessments. It does not change past assessment results.
Next Steps
Metric Profiles: make sure the metrics your conditions use are measured.
Metric Rules: review what each measured value means.
Quality Profiles: choose which rules raise the findings that gates count.
Quality Control: return to the Quality Control overview.
Last updated
Was this helpful?